FAQ’s
What Are You Looking For?
Frequently Asked Questions

This is a power line project. The project has been planned by the Ministry of Power, Government of India but will be executed by a private company. For details kindly refer to About us section.

Khavda IV C Transmission Limited (K4CPTL) is a power line project that has been planned by the Ministry of Power, Government of India and will be executed by a private company. The project will supply 7,000 MW of renewable power from Khavda renewable park in Kutch region of Gujarat to Maharashtra. The project has been discussed and agreed at various meetings held between the Ministry of Power, Central Electricity Authority, and Western Region Power Committee. For more details kindly refer to About us section. 

The project consists 5 transmission elements which will be constructed in Gujarat and Maharashtra states. The elements include i) a 765/400 kV substation in Maharashtra; ii) 765 kV South Olpad (GIS) – Boisar-II transmission line; iii) LILO of 765 kV Navsari (New) – Padghe (PG) transmission line; iv) 400 kV Boisar-II – Velgaon transmission line; v) and LILO of 400 kV Babhaleswar – Padghe transmission line. For details kindly refer to About us section.

S. NoElements of the projectLine length (km)StatesDistrictsPlanned date of commissioning
1South Olpad (GIS) – Boisar-II (GIS) 765 kV D/c line180.082GujaratSurat, Navsari, ValsadOct-2026
7.886UT of Dadra & Nagar Haveli and Daman and DiuDadra Nagar Haveli
50.152MaharashtraPalghar
2LILO of Navsari (New) – Padghe (PG) 765 kV D/c line at Boisar-IILoop in – 12.641MaharashtraPalgharOct-2026
Loop out – 12.899
3Boisar-II (Sec-II) – Velgaon (MH) 400 kV D/c25.121MaharashtraPalgharOct-2026
4LILO of Babhaleswar – Padghe (M) 400 kV D/c line at Boisar-II (Sec-I)58.14MaharashtraPalghar & ThaneOct-2026
5Establishment of 4×1500 MVA, 765/400 kV and 2×500 MVA, 400/220 kV Boisar-II (GIS) S/sNAMaharashtraPalgharOct-2026

The project aligns with the Government of India’s ambitious target of developing 500 GW of renewable energy capacity by 2030. By evacuating additional 7,000 MW of power flow from the renewable energy park in Gujarat, it will provide uninterrupted, reliable, and quality power supply to Maharashtra. For details kindly refer to Project Impact – Gujarat & Project Impact – Maharashtra section. 

This project has been approved by the Government of India and the route has been reviewed and finalised after conducting a detailed survey.

In case of transmission line project, there is no land acquisition or purchase made. The project only requires ‘Right of Way’ (ROW) access on the land parcel and the land title continues to remain with the landowner. However, the landowner is duly compensated for the surface damages (crop compensation) incurred during the construction activity as well as for the land area used under tower and conductor.

Further, land below transmission corridor can be utilized for farming, development of vegetable gardens, open storage, parking, development of park & playground, water & sewage mains or pipelines, walking/cycle trails.

Due to long span lengths between towers and their high ground clearance, transmission lines co-exist with nature. Although some felling of trees will be required during the construction work, natural regeneration is allowed to come up after the stringing work is completed on the towers.

Affected land owners will be paid compensation as per the government policy. Government of Gujarat and Government of Maharashtra have released guidelines for the compensation payment of transmission line projects. The guidelines for concerned states can be accessed in the Download section. 

Transmission lines will be safe even in monsoon if a minimum distance of 5.5 meters is maintained vertically and horizontally. New transmission lines are built with a grounded shield wire along the top of the poles, above the conductors, to protect the line from lightning.

The project is absolutely safe for humans, animals, and property. All safety related measures are taken during and after the execution of the project. Electricity does not run through transmission towers. Further, earthing is provided to each tower for protection from lightning strikes.